The chain locker bulkhead has been cut with the access hatch included. Framing strips still need to be glued in place and finished, after which temporary screws will be removed. The pictures show the bulkhead tempararily in place. Final fixing will only take place once the inside of the chain locker has been finished off.
Wednesday, August 17, 2011
Friday, August 12, 2011
Chain Locker and Forepeak.
Floors and bulkheads have been cut and fitted and are ready for final fixing, once sealing of timber in the forepeak and chain locker has been done. Also before final fitting is done the galvanic protection cable to the bow fitting needs to be inserted as well as the chain locker drainage to the sump. The pictures show the floors of the chain locker and forepeak cubby temporary in place as well as the chain locker bulkhead which has been cut but still needs the hatch to be cut out and finished.